Archive

Archive for the ‘Construction’ Category

Pier and Beam Foundations

March 30th, 2009

Several people have asked me about David Weekley’s pier and beam construction process. So it took some time, but I went through all of my pics and pulled a collection that shows how they do it. Let me also preface this by saying I’m not a construction guy, but I play one on TV. I learned what I could from the real construction folks on the job, so take the terms and definitions I use lightly!

The first ingredient is an empty lot… :)
1_picture-044_600x450

After a series of surveys and soil tests, an engineering company (external to David Weekley) determines how deep the piers need to go into the ground. In the Houston area, especially land in the 100 and 500 year flood plains, there is a lot of moisture deep down in the soil. This can cause problems with the foundation settling etc, so it is very important to get the pier depth correct. In our case, for a 3600sq ft 2 story home, the crews dug 15 holes, each 16 to 18 feet deep. At the bottom of each hole, a special machine makes a “bell shape” so the concrete spreads out under ground. Fortunately for us, the holes did not fill up with water. Apparently ground water can cause issues when trying to pour the piers.
2_picture-110_600x450

Here’s a pic of the machine that created the initial 18 foot holes. It has a massive drill bit and long shaft to dig deep and pull dirt out of the ground.
3_picture-118_600x450

This is the machine that creates the “bell shape” at the bottom of each hole. It’s basically the same machine with a different drill bit. The bit has a couple of blades housed within a metal casing. When the bit gets to the bottom of the hole, the blades fan out to create the open space. Ultimately, the concrete poured into each hole will spread out at the bottom for steady footing.
4_picture-117_600x450

Before they pour the concrete piers, they create columns of re-bar and insert them into each hole. Just like what you see in buildings and roadways, the re-bar helps reinforce the concrete.
5_picture-138_600x450

After the piers have been poured, the foundation crew builds additional forms for more concrete. They put down a re-bar reinforced outer wall around the entire home footprint, and they also pour “pads” on top of each pier. Below you can see outer wall (and in our case the base of the front porch in foreground). Out in the middle, you can see the forms for each pad.
6_picture-145_600x450

Here’s a close up of a pad form on top of the pier…
7_picture-149_600x450

This is a pic of the entire foundation after they poured concrete… Not your “typical” post tension slab.
8_picture-179_600x450

Close up of the pads with concrete. Here you can also see the PVC pipes for dirty water heading to the sewer. This is one of the benefits of pier and beam… if you have any plumbing issues, it’s easier for plumbers to access proplem areas.
9_picture-183_600x450

At this point, all the ground work is complete and the crew will build a concrete block structure on top of the foundation. The exterior blocks will eventually have Acme brick attached to them, and 1/2 inch diameter bolts are also sunk in to the exterior blocks to secure the wood frame structure. Here you can see the pads now have blocks stacked on them. The blocks have concrete poured down the interior, so the complete pier is quite solid. On top of each pier you can see metal strips that are used to secure the beams.
10_dsc00014_600x450

Here’s a close up of the foundation. Notice the bolts around the outside, metal straps on each pier, and water proof ground cover to prevent ground humidity from damaging the underside of the house.
11_dsc00040_600x450

Let the sub-flooring begin! Pressure treated lumber is used to create the boundary between the blocks and subfloor. This wood is secured with industrial glue and the exterior bolts. A honeycomb structure of beams is created on top of the external wall and piers.
12_dsc00044_600x450

Here’s a close up of the sub-floor. The underside of the floor will be covered with insulation (hung by hooks), and the entire bottom will then be covered by a house wrap material.
13_dsc00085_600x450

And this is what it all comes down to… a pier and a beam! Here you can see how the metal straps wrap around the base of each beam.
14_dsc00082_600x800

The framing can now begin on the rest of your home…
15_dsc00213_600x450

On top of the subfloor, David Weekley uses 1 1/2 inch thick decking material for the floor. These pieces actually interlock with each other. The floor is initially nailed down, but ultimately screwed down after the roof is complete.
16_dsc00258_600x450

Since the subfloor is wood and not concrete (like traditional slab), when installing tile, David Weekley uses Hardie backer board to prevent tiles and grout from cracking.
dsc01222_600x800

Externally, you can now see the flood vents and brick walls…
17_dsc01169_600x450

And here’s the “almost” finished product. Still need a driveway, sidewalk and landscaping… in addition to finishing the front porch!
18_dsc01572_600x450

So this was a little longer than my normal posts, but hopefully you have an idea what goes in to building on pier and beam. David Weekley has done an excellent job on our project, and I highly recommend them to anyone reading this!

Construction

Shelley’s Kitchen

March 19th, 2009

After our visit to the pediatrician today, we stopped by the construction site to check on progress. Shelley got to see the kitchen counter tops and tile work for the first time in person. Needless to say, it was a nice to get outside and enjoy the beautiful weather.

Shelley checks out the view from our front door.
dsc01566_600x800

And likes what she sees in the kitchen…
dsc01567_600x450

Here’s the current view from the street. It looks like the driveway and sidewalk are about to be poured!
dsc01569_600x450

Growing up I always wondered where the sidewalk ends…
dsc01565_600x450

Construction

Paint, cabinets and counter tops!

March 7th, 2009

Things have been moving pretty quickly over the last few weeks. Our builder knows the baby is due shortly, so they are working hard to get things done.  Here are some pics to get everyone up to speed!

Current view from the street.
Most of the brick work is complete… still need to finish the front steps and porch.
dsc01191_600x450

Garage exterior is almost complete.  The painters will soon finish the trim!dsc01183_600x450

First round of interior paint is done. The walls look a little bit darker because the windows up front are playing tricks with the camera, but the house is starting to have a nice warm feel to it.  Here you are looking from the family room towards the kitchen (right), dining room (front), hallway to master and nursery (bottom left).
dsc01205_600x450

Cabinets and counter tops are going in… The center island here will eventually have a gas cook top. Double ovens in the back wall, warming drawer below and microwave to the top right.
dsc01220_600x450

It took 5 big guys to move the final slab of granite inside for cutting.  This piece will cover the kitchen sink area.
dsc01229_600x450

Here’s the tile work in our kitchen…
dsc01239_600x450

Last shot for this post.  The crew is setting travertine in the master bath…
dsc01241_600x450

Construction

Brick and Insulation

February 10th, 2009

Last week we passed our structural inspection from the City of Bellaire. Fifth time’s a charm, but the house is officially nuclear blast resistant as a result. Lot’s of additional reinforcements made. This was a big milestone for the project, so the crews were able to get started on brick, insulation and dry wall over the weekend!

The brick is stacked and ready to go on the front porch…
dsc00913_800x6002

The garage is just about done. Mortar is still wet, but only took 2 days and a couple thousand bricks!
dsc00930_800x600

Ohhh ahhh… Fluffy pink insulation!
dsc00878_800x600

Construction

The house is green!

January 24th, 2009

This week our house passed it’s Energy Star certification, earning a green stamp of approval.  David Weekley follows a great environmental program that ends up being about 35% more effecient than current Energy Star standards.  In addition to vinyl frame, argon insulated glass windows and TechShield roof decking, the house has two 15 SEER AC units with Puron R-410 refirgerant, upgraded R-value ducts and insulation. 

You can Google “U-Factor” to learn more about the numbers!
dsc00386_600x450

Here’s a shot of the TechSheild in the attic.
dsc00398_600x450

Foam insulation to seal the walls and prevent drafts.
dsc00600_600x450

Be green and clean!  For more on David Weekley’s environmental program click HERE!

Construction